This set of Construction Cost Estimation Multiple Choice Questions & Answers (MCQs) focuses on “Rate Analysis – Units and Dimensions”.
1. Single units work such as doors and windows are expressed in ________
a) numbers
b) metres
c) m2
d) m3
View Answer
Explanation: Single units work such as doors and windows are expressed in numbers. The units of measurement are generally classified basis on their nature, size and shape.
2. Work consisting of linear measurements like fencing which involve lengths is measured in __________
a) Kilograms
b) Running metres
c) m2
d) m3
View Answer
Explanation: Work consisting of linear measurements like fencing which involve lengths is measured in running metres. Other works which involve length are cornice, handrail, etc.
3. Works like whitewashing and plastering are measured in ________
a) m2
b) Metres
c) Litres
d) m3
View Answer
Explanation: Works like whitewashing and plastering are measured in m2. These works consist of areal surface measurements and involve area and hence these are measured in square metres.
4. Works like earthwork and cement concrete are measured in ________
a) Square metres
b) Metres
c) Litres
d) Cubic metres
View Answer
Explanation: Works like earthwork and cement concrete are measured in cubic metres. These works contain cubical contents and involve volumes and hence these are measured in m3.
5. Unit of measurement for damp proof course is ____________
a) Sqm
b) Cum
c) Number
d) Kg
View Answer
Explanation: Unit of measurement for the damp proof course is sqm. While, the unit of measurement of brickwork in foundation, plinth, superstructure and arches is cum.
6. Unit of measurement of iron holdfasts in steelwork is ___________
a) Sqm
b) Number
c) Metres
d) Quintal
View Answer
Explanation: Unit of measurement of iron holdfasts and iron railing in steelwork is quintal. However, the unit of measurement of grills in steelwork is sqm.
7. Unit of measurement of asbestos cement sheet roofing is __________
a) Sqm
b) Kilograms
c) Metres
d) Number
View Answer
Explanation: Unit of measurement of asbestos cement sheet roofing is sqm and its unit of payment is per sqm. Unit of measurement of centering and shuttering formwork is also sqm.
8. Unit of measurement of rainwater pipe is ________
a) Cum
b) Litres
c) Number
d) Running metres
View Answer
Explanation: Unit of measurement of rainwater pipe is running metres. The unit of payment of rainwater pipes is per RM.
9. The unit of measurement of pointing, painting and varnishing (no. of coats specified) is cum.
a) True
b) False
View Answer
Explanation: The unit of measurement of pointing, painting and varnishing (no. of coats specified) is sqm. The unit of payment is per sqm.
10. The rules for measurement of all items are described in _______
a) IS-1993
b) IS-1896
c) IS-1200
d) IS-1987
View Answer
Explanation: The rules for measurement of all items are described in IS-1200. It is specified that in booking, the order should be in sequence of length, breadth and height.
11. As per the rules for measurement of items, it is specified that the areas should be measured to the nearest ________
a) 0.1 sq m
b) 0.25 sq m
c) 0.01 sq m
d) 0.85 sq m
View Answer
Explanation: As per the rules for the measurement of items, it is specified that the areas should be measured to the nearest 0.01 sq m. It is also specified that the cubic contents should be measured to the nearest 0.01 cum.
Sanfoundry Global Education & Learning Series – Construction Cost Estimation.
To practice all areas of Construction Cost Estimation, here is complete set of 1000+ Multiple Choice Questions and Answers.
If you find a mistake in question / option / answer, kindly take a screenshot and email to [email protected]
- Check Construction and Building Materials Books
- Check Civil Engineering Books
- Practice Civil Engineering MCQs
- Apply for Civil Engineering Internship