Construction Cost Estimation Questions and Answers – Types of Estimates

This set of Construction Cost Estimation Multiple Choice Questions & Answers (MCQs) focuses on “Types of Estimates”.

1. Which of the following data is not required to prepare an estimate?
a) Amplitude
b) Drawings
c) Specifications
d) Rates
View Answer

Answer: a
Explanation: For preparing an estimate, data such as drawings, detailed specifications, rates, etc. is required. The drawings needed to prepare the estimate include plans, sections, elevations, etc.

2. Estimating is the technique of calculating the various quantities and is needed for controlling the expenditure during the execution of the work.
a) True
b) False
View Answer

Answer: a
Explanation: Estimating is the process of calculating the various quantities and their cost in the building construction. It is needed for controlling the expenditure during the execution of the work.

3. The process of working out the cost per unit of each item is known as _________
a) Work
b) Sheet
c) Data
d) Analysis
View Answer

Answer: c
Explanation: The preparation of a detailed estimate comprises of working out quantities of different items of work and then determining the cost of each item. The process of working out the cost per unit of each item is known as data.
advertisement
advertisement

4. While fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per __________
a) Special Data Book
b) Standard Data Book
c) Special Data Record
d) Specific Data Record
View Answer

Answer: b
Explanation: While fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per the Standard Data Book. However, the rates of labour and materials are obtained from the current standard scheduled of rates.

5. In the case of works which require some special types of equipment, an amount of ______ percent of the estimated cost is given.
a) 1-2
b) 5-9
c) 12-18
d) 16-20
View Answer

Answer: a
Explanation: In the case of works that require some special types of equipment, an amount of 1-2 percent of the estimated cost is given. While preparing a detailed estimate, it is also important to select a suitable site of work to reduce damage during the loading and unloading of materials.
Sanfoundry Certification Contest of the Month is Live. 100+ Subjects. Participate Now!

6. Which of the following is not a method used for preparing approximate estimates?
a) Cubical contents method
b) Unit base method
c) Plinth area method
d) Cylindrical base method
View Answer

Answer: d
Explanation: There are various methods used for preparing approximate estimates. These are the plinth area method, unit base method and cubical contents method. An approximate estimate is needed for studying various aspects of the work of the project.

7. In the plinth area method, the cost of construction is computed by the multiplication of ________
a) Plinth length and rate
b) Plinth breadth and rate
c) Plinth area and plinth area rate
d) Plinth volume and plinth length rate
View Answer

Answer: c
Explanation: In the plinth area method, the cost of construction is computed by the multiplication of plinth area and plinth area rate. This area is calculated by multiplying the length and the breadth.
advertisement

8. As per IS 3861-1966, which of the following areas should not be included while calculating the plinth area of a building?
a) Porches of non-cantilever type
b) Area of barsati at terrace level
c) Area of walls at floor level
d) Area of lofts
View Answer

Answer: d
Explanation: As per IS 3861-1966, the areas which should be included while calculating the plinth area of a building are porches of non-cantilever type, area of barsati at terrace level, area of walls at floor level, etc. However, the area of lofts should not be included.

9. For the preparation of approximate estimates, cubical contents method is more accurate than the unit base method and plinth area method.
a) True
b) False
View Answer

Answer: a
Explanation: For the preparation of approximate estimates, cubical contents method is more accurate than the unit base method and plinth area method. Cubical contents method is usually used for multi-storeyed buildings.
advertisement

10. In the cubical contents method, the cost of a structure is computed by the multiplication of total cubic contents and _______
a) Area of building
b) Volume of building
c) Local cubic rate
d) Length of building
View Answer

Answer: c
Explanation: The cost of a structure in the cubical contents method is determined by the multiplication of total cubic contents with the local cubic rate. Therefore, the cost of the building is calculated by multiplying the volume of buildings with the rate per unit volume.

Sanfoundry Global Education & Learning Series – Construction Cost Estimation.

To practice all areas of Construction Cost Estimation, here is complete set of 1000+ Multiple Choice Questions and Answers.

If you find a mistake in question / option / answer, kindly take a screenshot and email to [email protected]

advertisement
advertisement
Subscribe to our Newsletters (Subject-wise). Participate in the Sanfoundry Certification contest to get free Certificate of Merit. Join our social networks below and stay updated with latest contests, videos, internships and jobs!

Youtube | Telegram | LinkedIn | Instagram | Facebook | Twitter | Pinterest
Manish Bhojasia - Founder & CTO at Sanfoundry
Manish Bhojasia, a technology veteran with 20+ years @ Cisco & Wipro, is Founder and CTO at Sanfoundry. He lives in Bangalore, and focuses on development of Linux Kernel, SAN Technologies, Advanced C, Data Structures & Alogrithms. Stay connected with him at LinkedIn.

Subscribe to his free Masterclasses at Youtube & discussions at Telegram SanfoundryClasses.