Petroleum Production Operations Questions and Answers – Squeeze Cementing – Normal Operational Procedure

This set of Petroleum Production Operations Multiple Choice Questions & Answers (MCQs) focuses on “Squeeze Cementing – Normal Operational Procedure”.

1. Squeeze packers are used for low-pressure squeeze cementing.
a) True
b) False
View Answer

Answer: b
Explanation: The statement is true. Squeeze packers are specially designed to be used for low-pressure squeeze cementing. Those zones where pressures are anticipated along with other perforations then squeeze tools are used.

2. When is the retrievable squeeze packers used?
a) Resetting permits flexibility and to find casing leak
b) Low-pressure application
c) High-pressure application
d) At the time of Drilling
View Answer

Answer: a
Explanation: A retrievable squeeze packer allows flexibility of the resetting and at the same time it can detect the casing leak. By using this squeeze cementing can be done very easily at the casing leak and less rig time is required for this purpose.

3. Why does coiled tubing have a faster rate of penetration than rotary drilling rig?
a) It doesn’t need a special crew
b) Since connection needs to be made
c) It is a continuous reel
d) It requires more joined pipes to connect with
View Answer

Answer: c
Explanation: Coiled tubing has a faster rate of penetration than rotary drilling rig because it is a continuous reel. So, very little time is required for the operations. Coiled tubing refers to a very long metal pipe that is continuous in nature without any joint.
advertisement
advertisement

4. The Cement Retainer is a drillable packer.
a) True
b) False
View Answer

Answer: a
Explanation: The statement is true. Drillable packers are also called Cement Retainers. Cement Retainers consistently contain well pressures at elevated temperatures and pressures. This packer is used in squeeze cementing purposes.

5. What is wait on cement?
a) The time required for cementing
b) The time required for casing placement
c) The time required for the cement to solidify
d) The time required for the cement to just place around the casing
View Answer

Answer: b
Explanation: Wait on cement is the time required for the cement slurry to solidify. By allowing the cement slurry sufficient time, the cement slurries develop compressive strength. Thus it allows further activities.
Sanfoundry Certification Contest of the Month is Live. 100+ Subjects. Participate Now!

Sanfoundry Global Education & Learning Series – Petroleum Production Operations.

To practice all areas of Petroleum Production Operations, here is complete set of 1000+ Multiple Choice Questions and Answers.

advertisement

If you find a mistake in question / option / answer, kindly take a screenshot and email to [email protected]

advertisement
advertisement
Subscribe to our Newsletters (Subject-wise). Participate in the Sanfoundry Certification contest to get free Certificate of Merit. Join our social networks below and stay updated with latest contests, videos, internships and jobs!

Youtube | Telegram | LinkedIn | Instagram | Facebook | Twitter | Pinterest
Manish Bhojasia - Founder & CTO at Sanfoundry
Manish Bhojasia, a technology veteran with 20+ years @ Cisco & Wipro, is Founder and CTO at Sanfoundry. He lives in Bangalore, and focuses on development of Linux Kernel, SAN Technologies, Advanced C, Data Structures & Alogrithms. Stay connected with him at LinkedIn.

Subscribe to his free Masterclasses at Youtube & discussions at Telegram SanfoundryClasses.