1. When using coil tubing, what is the name of the unit used to push/pull?
a) Injector
b) Mud pump
c) Charge pump
d) Top drive
View Answer

Answer: a
Explanation: Injector is used to push/pull while using the coil tubing. Coiled tubing refers to a very long metal pipe that is continuous in nature without any joint which is supplied from the spooled reel. Coil tubing injector is the equipment used for the gripping purpose and provides the forces needed for deployment of the tube into and out of the wellbore.

2. In the petroleum industry, Coiled Tubing is faster or slower than a workover rig?
a) Slower
b) Same
c) Faster
d) Can’t say
View Answer

Answer: c
Explanation: In the petroleum industry, Coiled Tubing is faster than a workover rig. Coiled tubing refers to a very long metal pipe that is continuous in nature without any joint. So, very little time is required for the operations.

3. When are the drillable packers used?
a) Resetting permits flexibility and to find casing leak
b) Low-pressure application
c) High-pressure application
d) To abandon the lower perforation to abandon the lower perforation
View Answer

Answer: d
Explanation: Drillable packers used to abandon the lower perforation. In some of the cases, drillable packers are used to isolate the lower perforations when the upper zone is to be cemented.
advertisement
advertisement

4. How far is the cement brought up the annulus?
a) To the surface
b) Min 200-500 ft above the shoe
c) Quarter Way up the wellbore
d) Min 1200-1500 ft above the shoe
View Answer

Answer: b
Explanation: Cement brought up the annulus with a measurement minimum of 200-500 ft above the shoe. Otherwise, the cost will be higher because of unnecessary cement. The upper part generally has the strength to withstand itself.

5. Squeeze cementing is a dehydration process.
a) True
b) False
View Answer

Answer: a
Explanation: The statement is true. Squeeze cementing is highly used in the oil and gas industry. In the squeeze cementing process, cement is squeezed inside the particular zone at which some types of problems exist. This job can be done at any time. The zone is isolated from the place in which the squeeze cementing needs to be done by using packers.
Sanfoundry Certification Contest of the Month is Live. 100+ Subjects. Participate Now!

Sanfoundry Global Education & Learning Series – Petroleum Production Operations.

To practice all areas of Petroleum Production Operations, here is complete set of 1000+ Multiple Choice Questions and Answers.

advertisement

If you find a mistake in question / option / answer, kindly take a screenshot and email to [email protected]

advertisement
advertisement
Subscribe to our Newsletters (Subject-wise). Participate in the Sanfoundry Certification contest to get free Certificate of Merit. Join our social networks below and stay updated with latest contests, videos, internships and jobs!

Youtube | Telegram | LinkedIn | Instagram | Facebook | Twitter | Pinterest
Manish Bhojasia - Founder & CTO at Sanfoundry
Manish Bhojasia, a technology veteran with 20+ years @ Cisco & Wipro, is Founder and CTO at Sanfoundry. He lives in Bangalore, and focuses on development of Linux Kernel, SAN Technologies, Advanced C, Data Structures & Alogrithms. Stay connected with him at LinkedIn.

Subscribe to his free Masterclasses at Youtube & discussions at Telegram SanfoundryClasses.