Waste Water Engineering Questions and Answers – Activated Sludge Process – 2

This set of Waste Water Engineering online test focuses on “Activated Sludge Process – 2”.

1. Calculate the volume of the aeration tank required for the following data:
Flow: 800 m3/d
BOD: 1000 mg/L
F/M ratio: 0.15(extended aeration)
MLSS : 3500 mg/L
a) High sludge volume index
b) Low sludge volume index
c) Low oxygen demand
d) Floc formation is less
View Answer

Answer: a
Explanation: Readily biodegradable COD if it is high in the influent, then the sludge volume index will be very high. Also this high level of COD would contribute to the floc formation. This also results in higher oxygen demand.

2. For the removal of BOD through Activated Sludge Process (ASP) what would be the Solid retention time considered?
a) 18 hours
b) 1-2 days
c) 10 hrs
d) 3 days
View Answer

Answer: b
Explanation: For the removal of BOD through ASP, the solid retention time considered is 1-2 days. However, this depends on the temperature. In case the temperature is very low, then the solid retention time considered would be around 5-6 days.

3. For the conversion of particulate organics through Activated Sludge Process (ASP) what would be the Solid retention time considered?
a) 18 hours
b) 1-2 days
c) 2-4 days
d) 5 days
View Answer

Answer: c
Explanation: For the conversion of particulate organics through ASP, the Solid retention time considered would be 2-4 days. Particulate organic carbon is defined as those materials that can pass through a filter which is of size 0.7 to 0.22 um. This usually constitutes soil organic matter that includes plant material, pollen etc.
advertisement
advertisement

4. For the development of flocculent biomass for treating domestic water through Activated Sludge Process (ASP) what would be the Solid retention time considered?
a) 18 hours
b) 4 days
c) 10 hrs
d) 1-3 days
View Answer

Answer: d
Explanation: For the development of flocculent biomass for treating domestic water through the Activated Sludge Process (ASP), the solid retention time considered is 1-3 days. In case it is industrial waste water, the retention time considered would be different. The difference is due to the difference in concentration of BOD in the influent.

5. For the development of flocculent biomass for treating industrial water through Activated Sludge Process (ASP) what would be the Solid retention time considered?
a) 18 hours
b) 3-5 days
c) 20 hrs
d) 1-3 days
View Answer

Answer: d
Explanation: For the development of flocculent biomass for treating industrial water through Activated Sludge Process (ASP), the solid retention time considered is 3-5 days. This is a little higher than that of the Solid retention time required to treat domestic waste water. The difference is because the industrial waste water constitutes higher BOD values.

6. For the removal of nitrogen completely through Activated Sludge Process (ASP) what would be the Solid retention time considered?
a) 3-18 days
b) 1-2 days
c) 12 hours
d) 18 hours
View Answer

Answer: b
Explanation: For the complete removal of Nitrogen through ASP, the solid retention time considered is 3-18 days. However, this depends on the temperature. In case the temperature is very low, then the solid retention time considered would be around 15-18 days. For higher temperatures, lower solid retention time is considered.

7. For the removal of phosphorous through Activated Sludge Process (ASP) what would be the Solid retention time considered?
a) 18 hours
b) 1-2 days
c) 10 hrs
d) 2-4 days
View Answer

Answer: d
Explanation: For the removal of phosphorous through ASP, the solid retention time considered is 2-4 days. However, this depends on the temperature. In case the temperature is very low, then the solid retention time considered would be around 4 days.
advertisement

8. What is the typical value of the F/M ratio considered for an ASP process?
a) 0.04 g/g.d
b) 0.1 g/g.d
c) 0.4 g/g.d
d) 0.01 g/g.d
View Answer

Answer: a
Explanation: The typical F/M value considered for an ASP process is 0.04 g/g.d. This is a process parameter that is used to characterize the operating conditions. Based on this F/M value the sizing of the aeration tanks for the ASP is carried out.

9. What is the typical value of the F/M ratio considered for an extended ASP process?
a) 0.04 g/g.d
b) 0.1 g/g.d
c) 0.4 g/g.d
d) 0.01 g/g.d
View Answer

Answer: b
Explanation: The typical F/M value considered for an extended ASP process is 0.1 g/g.d. This is a process parameter that is used to characterize the operating conditions. Based on this F/M value the sizing of the aeration tanks for the extended ASP is carried out.
advertisement

10. While designing an aeration tank for the ASP what is the volumetric organic loading rate considered?
a) 0.3-3
b) 0.03-0.2
c) 3-5
d) 5-7
View Answer

Answer: a
Explanation: While designing an aeration tank, the volumetric organic loading rate considered is 0.3-3. The volumetric organic loading rate is defined as the amount of COD/BOD applied to the aeration tank volume per day. It is expressed in kg BOD/COD m3d.

11. Calculate the BOD load for the following data.
Flow: 800 m3/d
BOD load: 1000 mg/L
a) 1000 kg/d
b) 800 kg/d
c) 500 kg/d
d) 1500 kg/d
View Answer

Answer: b
Explanation: The BOD load is calculated as Flow x BOD. Since the flow is in m3/d, the m3 is converted to L by multiplying by 1000. BOD load is expressed as Kg/L by dividing it by 1000000. BOD load = 800 x 1000 x 1000/ (1000×1000) = 800 Kg/d.

Sanfoundry Global Education & Learning Series – Waste Water Engineering.

To practice all areas of Waste Water Engineering for online tests, here is complete set of 1000+ Multiple Choice Questions and Answers.

If you find a mistake in question / option / answer, kindly take a screenshot and email to [email protected]

advertisement
advertisement
Subscribe to our Newsletters (Subject-wise). Participate in the Sanfoundry Certification contest to get free Certificate of Merit. Join our social networks below and stay updated with latest contests, videos, internships and jobs!

Youtube | Telegram | LinkedIn | Instagram | Facebook | Twitter | Pinterest
Manish Bhojasia - Founder & CTO at Sanfoundry
Manish Bhojasia, a technology veteran with 20+ years @ Cisco & Wipro, is Founder and CTO at Sanfoundry. He lives in Bangalore, and focuses on development of Linux Kernel, SAN Technologies, Advanced C, Data Structures & Alogrithms. Stay connected with him at LinkedIn.

Subscribe to his free Masterclasses at Youtube & discussions at Telegram SanfoundryClasses.