Surveying Questions and Answers – Curve Surveying – By Deflection Distances

This set of Surveying Multiple Choice Questions & Answers (MCQs) focuses on “Curve Surveying – By Deflection Distances”.

1. The method of deflection distances is used in which of the following cases?
a) Road surveys
b) Railway survey
c) Land survey
d) Town planning survey
View Answer

Answer: a
Explanation: The deflection distances method is having at most priority in case of road surveys as the curvature for joining parallel straights is to be done without any error.

2. The method of producing offsets from the chords can also be named as ____________
a) Rankine’s method
b) Bisection of chords
c) Deflection distances
d) Two-theodolite method
View Answer

Answer: c
Explanation: Deflection distances method is adopted in case of long curves, which generally implies in highways. Highway possess long curves which can’t be designed other than this method.

3. Which of the following indicates the formula used in deflection distances?
a) On = Cn + (Cn-1 + Cn)/2*R
b) On = Cn (Cn-1 + Cn)/2+R
c) On = Cn (Cn-1 – Cn)/2*R
d) On = Cn (Cn-1 + Cn)/2*R
View Answer

Answer: d
Explanation: The formula for the offsets by chords produced include, On = Cn (Cn-1 + Cn)/2*R. the value of n depends upon the number of chords introduced and C represents chord length, where R is the radius of the curve.
advertisement
advertisement

4. Which of the following process can be adopted as an alternative of theodolite?
a) Bisection of chords
b) Deflection distances
c) Ordinates by long chords
d) Rankine’s method
View Answer

Answer: b
Explanation: Theodolite usage is more in case of designing long curves. Long curve designation involves in lengthy calculation and developing number of chords, which can be done in deflection distances method. So, it can serve as an alternative.

5. Errors in deflection distances method are distributed to all the points.
a) True
b) False
View Answer

Answer: a
Explanation: The occurrence of errors in all cases is common, but in case of deflection distances method the error can be distributed all over the points. If the error is more, then the curve should be re-set.
Sanfoundry Certification Contest of the Month is Live. 100+ Subjects. Participate Now!

6. Closing error can also be known as __________
a) Absolute error
b) Zero error
c) Subjecting error
d) Discrepancy
View Answer

Answer: d
Explanation: Closing error occurs due to the mismatching of the beginning and the last points. It can be eradicated or reduced up to some extent based on the amount of error produced. It is also known as discrepancy.

7. While producing offsets by deflection distances method, the last offset must coincide with the beginning.
a) False
b) True
View Answer

Answer: b
Explanation: The occurrence of closing error depends on the closing the curve due to offsets. If the beginning point doesn’t coincide with the end point, then closing error may occur which may lead to re-setting of the entire curve.
advertisement

8. Determine the first offset if the chord length is given as 23.98m and the radius is given as 5.87m.
a) 84.98 m
b) 48.98 m
c) 48.89 m
d) 84.89 m
View Answer

Answer: b
Explanation: The value of offset can be given as O = C2 / 2*R. On substitution, we get
O = 23.982 / 2*5.87
O = 48.98m.

9. Find the value of last offset, if the lengths of first and second chords are given as 45.87m and 62.87m with radius of curve 69.76m and length of chain being 30m.
a) 38.987 m
b) 83.987 m
c) 38.697 m
d) 83.697 m
View Answer

Answer: d
Explanation: The value of offsets can be calculated by using,
On = Cn*(Cn – 1 + Cn) / 2*R, it can be simplified as
On = cꞌ*(C + cꞌ) / 2*R. On substitution, we get
On = 62.87*(30 + 62.87) / 69.76
On = 83.697m.
advertisement

10. Find the value of chord length if the offset is given as 36.54m and the radius include 3.43m.
a) 15.38 m
b) 51.83 m
c) 15.83 m
d) 87.54 m
View Answer

Answer: c
Explanation: From the deflection distances method, the value of chord length can be determined by
O = C2 / 2*R. On substitution, we get
36.54 = C2 / 2*3.43
C = 15.83m.

Sanfoundry Global Education & Learning Series – Surveying.

To practice all areas of Surveying, here is complete set of 1000+ Multiple Choice Questions and Answers.

If you find a mistake in question / option / answer, kindly take a screenshot and email to [email protected]

advertisement
advertisement
Subscribe to our Newsletters (Subject-wise). Participate in the Sanfoundry Certification contest to get free Certificate of Merit. Join our social networks below and stay updated with latest contests, videos, internships and jobs!

Youtube | Telegram | LinkedIn | Instagram | Facebook | Twitter | Pinterest
Manish Bhojasia - Founder & CTO at Sanfoundry
Manish Bhojasia, a technology veteran with 20+ years @ Cisco & Wipro, is Founder and CTO at Sanfoundry. He lives in Bangalore, and focuses on development of Linux Kernel, SAN Technologies, Advanced C, Data Structures & Alogrithms. Stay connected with him at LinkedIn.

Subscribe to his free Masterclasses at Youtube & discussions at Telegram SanfoundryClasses.