Railway Engineering Questions and Answers – Advantage & Essentials of Track Maintenance

This set of Railway Engineering Multiple Choice Questions & Answers (MCQs) focuses on “Advantage & Essentials of Track Maintenance”.

1. What should be done to improve the loose sleepers and the disturbed track geometry?
a) Replace it with new ones
b) Proper Maintenance
c) Additional parts should be added
d) Travel should not be permitted
View Answer

Answer: b
Explanation: Moving rails cause disturbance in the track geometry, effects alignment, gauge and other track components. Thus the track needs to be maintained which offers safe and comfortable journey.

2. Which of the following statements is false?
a) Life of track is independent of track maintenance
b) Tightening a bolt or Hammering dog spikes is a part of track maintenance
c) Maintenance saves money
d) Neglecting track maintenance may render it unrepairable
View Answer

Answer: a
Explanation: Regular track maintenance helps in reducing operation costs and fuel consumption. Proper maintenance of track ensures lesser wear and tear of components and thus increases the life of track.

3. What purpose does a Jim Crow serves in track maintenance?
a) Removes kinks
b) Removes rails
c) For digging out ballast
d) Squaring of sleepers
View Answer

Answer: a
Explanation: For Through packing examination of rails, sleepers and fastenings is done. The defective sleepers are removed and loose fastenings are tightened. A Jim Crow is used to remove any kinks if present in the rail.
advertisement
advertisement

4. How is gauge adjustment done in case of wooden sleepers?
a) With keys
b) Replacing the gauge components
c) Realignment
d) Refitting the dog spikes at a new location
View Answer

Answer: d
Explanation: In Wooden sleepers gauge adjustments should be avoided. This is because it can be done only by removing the dog spikes and refitting them at some other location. New holes are bored and spikes are re-driven.

5. Cotters are used for the gauge adjustment of which of the following types of sleeper?
a) CST-9 sleepers
b) Wooden sleepers
c) Steel trough sleepers
d) Concrete sleepers
View Answer

Answer: a
Explanation: Gauge adjustment is case of CST-9 sleepers is done with the help of cotters. Gauge can be adjusted to a maximum extent of -3mm to +10mm. Keys are used in case of steel trough sleepers.
Sanfoundry Certification Contest of the Month is Live. 100+ Subjects. Participate Now!

6. Packing of sleepers is done by applying the scissor packing method.
a) True
b) False
View Answer

Answer: a
Explanation: Packing of sleepers is done by scissor packing method. While the packing is carried out the second rail is brought to correct cross levels to ensure proper surfacing of the track. The top and alignment should be checked carefully after packing.

Sanfoundry Global Education & Learning Series – Railway Engineering.

advertisement

To practice all areas of Railway Engineering, here is complete set of 1000+ Multiple Choice Questions and Answers.

If you find a mistake in question / option / answer, kindly take a screenshot and email to [email protected]

advertisement
advertisement
Subscribe to our Newsletters (Subject-wise). Participate in the Sanfoundry Certification contest to get free Certificate of Merit. Join our social networks below and stay updated with latest contests, videos, internships and jobs!

Youtube | Telegram | LinkedIn | Instagram | Facebook | Twitter | Pinterest
Manish Bhojasia - Founder & CTO at Sanfoundry
Manish Bhojasia, a technology veteran with 20+ years @ Cisco & Wipro, is Founder and CTO at Sanfoundry. He lives in Bangalore, and focuses on development of Linux Kernel, SAN Technologies, Advanced C, Data Structures & Alogrithms. Stay connected with him at LinkedIn.

Subscribe to his free Masterclasses at Youtube & discussions at Telegram SanfoundryClasses.