Power Systems Questions and Answers – Inductance of a Single-Phase Two-Wire Line – 2

This set of Power Systems Interview Questions and Answers focuses on “Inductance of a Single-Phase Two-Wire Line – 2”.

1. A 10 MVA, 11 kV alternators has positive, negative and zero sequence reactance of 25%, 40%, 10% respectively. The resistance that must be placed in the neutral such that zero sequence of fault current for a single phase to ground fault will not exceed the rated line current in pu is ______
a) 0.22
b) 0.11
c) 0.16
d) 0.97
View Answer

Answer: a
Explanation: Zero sequence of fault current for single phase to ground fault current in pu is 0.22

2. A 10 MVA, 11 kV alternator has positive, negative and zero sequence reactance of 25%, 40%, 10% respectively. The resistance that must be placed in the neutral such that fault current for a single phase to ground fault will not exceed the rated line current in pu is _____________
a) 0.97
b) 0.22
c) 0.87
d) 0.45
View Answer

Answer: a
Explanation:
Current for single phase to ground fault will not exceed rated line current in pu is 0.97

3. A 10 MVA, 11 kV alternator has positive, negative and zero sequence reactance of 25%, 40%, 10% respectively. The resistance that must be placed in the neutral such that fault current for a single phase to ground fault will not exceed the rated line current in ohms is __________
a) 11.7
b) 12.8
c) 2.66
d) 5.2
View Answer

Answer: a
Explanation:
Current for single phase to ground fault will not exceed rated line current is 11.7
advertisement
advertisement

4. (I) Unsymmetrical spacing configurations cause the line interference.
(II) Unsymmetrical spacing causes the voltage induction in the communication lines.
a) (I) and (II) are valid
b) Only (I) is valid
c) Only (II) is valid
d) Both are invalid
View Answer

Answer: a
Explanation: Both the statements are correct as the unsymmetrical spacing causes the unbalanced voltage generation.

5. (I) Unsymmetrical spacing configurations cause the line interference.
(II) Unsymmetrical spacing causes the voltage induction in the communication lines.
The above problems can be eliminated by ________
a) transposition
b) parallel lines
c) three phase
d) all of the mentioned
View Answer

Answer: a
Explanation: Transposition meaning exchange of conductors will cause the net voltage induced in the other lines to be zero as the net inductance remains constant.
Sanfoundry Certification Contest of the Month is Live. 100+ Subjects. Participate Now!

6.Transposition is the mean to balance ____________
a) Inductance
b) Voltage
c) Current
d) All of the mentioned
View Answer

Answer: a
Explanation: Transposition primarily balances the inductances in the line thus causing a constant inductance throughout the line.

7. Over the length of one transposition cycle of a power line, the total flux linkages of a nearby telephone line are zero for the unbalanced three phase currents.
a) True
b) False
View Answer

Answer: b
Explanation: For an unbalanced supply, there will be non zero flux zero flux linkages in the telephone lines.
advertisement

8. Over the length of one transposition cycle of a power line, the total flux linkages of a nearby telephone line are zero for the balanced three phase currents.
a) The above statement is valid
b) The above statement is invalid
c) It can’t be concluded
d) The above statement is valid for all conditions.
View Answer

Answer: a
Explanation: Its valid only with balanced systems.

Sanfoundry Global Education & Learning Series – Power Systems.

advertisement

To practice all areas of Power Systems for Interviews, here is complete set of 1000+ Multiple Choice Questions and Answers.

If you find a mistake in question / option / answer, kindly take a screenshot and email to [email protected]

advertisement
advertisement
Subscribe to our Newsletters (Subject-wise). Participate in the Sanfoundry Certification contest to get free Certificate of Merit. Join our social networks below and stay updated with latest contests, videos, internships and jobs!

Youtube | Telegram | LinkedIn | Instagram | Facebook | Twitter | Pinterest
Manish Bhojasia - Founder & CTO at Sanfoundry
Manish Bhojasia, a technology veteran with 20+ years @ Cisco & Wipro, is Founder and CTO at Sanfoundry. He lives in Bangalore, and focuses on development of Linux Kernel, SAN Technologies, Advanced C, Data Structures & Alogrithms. Stay connected with him at LinkedIn.

Subscribe to his free Masterclasses at Youtube & discussions at Telegram SanfoundryClasses.