1. In slab culverts RCC slab is placed over abudment of __________
a) Masonry
b) Pre stressed
c) Steel
d) Composite
View Answer

Answer: a
Explanation: Generally the RCC slab is placed over abudment made of masonry only because other materials are costly.

2. The span of RCC slab is limited to __________
a) 1 m
b) 1.5 m
c) 2.0 m
d) 3.0 m
View Answer

Answer: d
Explanation: The span of the RCC slab is usually limited to 3 m as it may have maintenance problems.

3. What is the minimum diameter used in pipe culverts?
a) 25 cm
b) 35 cm
c) 45 cm
d) 75 cm
View Answer

Answer: d
Explanation: The minimum diameter of the pipe culverts used is 75 cm made of steel or RCC, usually RCC is only used as steel corrodes.
Note: Join free Sanfoundry classes at Telegram or Youtube
advertisement
advertisement

4. The GWT should be at a distance of _______ from ground level.
a) 0.5 m
b) 0.6 m
c) 1.2 m
d) 5.0 m
View Answer

Answer: c
Explanation: The preferred distance from the ground level is 1.2m, however it is not a problem where ground water table is very low.

5. The total interruption to traffic in a year should not exceed __________
a) 45 days
b) 40 days
c) 30 days
d) 15 days
View Answer

Answer: d
Explanation: The interruption should be kept as low as possible if unavoidable then we must provide it for 15 days.
Take Highway Engineering Practice Tests - Chapterwise!
Start the Test Now: Chapter 1, 2, 3, 4, 5, 6, 7, 8, 9, 10

6. The clay seal may be provided if the seepage zone is at a depth of less than __________
a) 1.2 m
b) 1.0 m
c) 0.9 m
d) 0.6m to 0.9 m
View Answer

Answer: d
Explanation: The clay seal may be construed if the seepage zone is at a depth of less than 0.6 m to 0.9 m.

7. The capillary control can be controlled by how many methods?
a) One
b) Two
c) Three
d) Four
View Answer

Answer: b
Explanation: The capillary control can be controlled by two methods called granular capillary cut off and impermeable capillary cut off.
advertisement

8. To fulfill the adequate permeability the D15 of filter/D15 of foundation ratio should be greater than __________
a) 5
b) 10
c) 15
d) 20
View Answer

Answer: a
Explanation: For adequate permeability, the ratio of the D15 of filter/D15 of foundation should be greater than 5.

9. The D85 point size is given by __________
a) Dp
b) 2Dp
c) 3Dp
d) 4Dp
View Answer

Answer: b
Explanation: The D85 point size of the filter is given by the value 2Dp.
advertisement

10. The loss of water from leaves present on embankment is called __________
a) Evaporation
b) Transpiration
c) Sublimation
d) Boiling
View Answer

Answer: b
Explanation: The vegetation is provided on the embankment as they can absorb the water during heavy rain, and the loss is termed as transpiration.

Sanfoundry Global Education & Learning Series – Highway Engineering.

To practice all areas of Highway Engineering, here is complete set of 1000+ Multiple Choice Questions and Answers.

advertisement
advertisement
Subscribe to our Newsletters (Subject-wise). Participate in the Sanfoundry Certification contest to get free Certificate of Merit. Join our social networks below and stay updated with latest contests, videos, internships and jobs!

Youtube | Telegram | LinkedIn | Instagram | Facebook | Twitter | Pinterest
Manish Bhojasia - Founder & CTO at Sanfoundry
Manish Bhojasia, a technology veteran with 20+ years @ Cisco & Wipro, is Founder and CTO at Sanfoundry. He lives in Bangalore, and focuses on development of Linux Kernel, SAN Technologies, Advanced C, Data Structures & Alogrithms. Stay connected with him at LinkedIn.

Subscribe to his free Masterclasses at Youtube & technical discussions at Telegram SanfoundryClasses.