This set of Highway Engineering Multiple Choice Questions & Answers (MCQs) focuses on “Preparation of Detailed Project Report”.
1. The DPR consists of how many components?
a) One
b) Two
c) Three
d) Four
View Answer
Explanation: The DPR consists of report, estimate and drawing making it three components.
2. The first step in the detail checklist of DPR is ___________
a) Executive summary
b) Background
c) Roadway features
d) General details of the project
View Answer
Explanation: The executive summary is the details that are prepared after the field work in the site has been completed.
3. The name of the work and project details is managed under which category of DPR?
a) Executive summary
b) Background
c) Roadway details
d) General details
View Answer
Explanation: In the background of the project name, scope of service, data source, importance and economics of the project are managed.
4. The roadway features include the study of ___________
a) Accidental analysis
b) Geometric design
c) Route alignment
d) Safety
View Answer
Explanation: The roadway features are studied for route selection, route alignment, environmental factors, cross section elements, traffic studies.
5. The final step in the specifications and design of roadway elements is ___________
a) Specifications
b) Design elements
c) Geometric design
d) Safety and audit of the design elements
View Answer
Explanation: After all the design requirements are calculated and if they are finalized the last step is to check the safety of the design elements.
6. Which of the following is not a structure constructed for drainage purposes?
a) Aqueduct
b) Syphon aqueduct
c) Level crossing
d) Pitot tube
View Answer
Explanation: A pitot tube is an instrument which is used to measure the velocity of water in rivers and streams.
7. The strength of the materials can be checked by ___________
a) Visual inspection
b) Quality control
c) By asking the manufacturer
d) By referring to various codes
View Answer
Explanation: The materials should always be tested in a laboratory for accurate and exact results quality check should always be conducted.
8. For small projects which type of method is used for the calculation of project time?
a) Milestone chart
b) Bar chart
c) PERT
d) CPM
View Answer
Explanation: For small projects, the completion time may be evaluated by bar chart, milestone chart may be used when all the critical activities are required.
9. Which of the following is prepared first during estimate?
a) Schedule of rates
b) Rate analysis
c) Detailed cost estimate
d) Detailed project
View Answer
Explanation: The first step in the preparation of estimates is a schedule of rates followed by rate analysis and detailed cost estimate.
10. The site amenities are covered under which of the items of DPR?
a) Background
b) Abstract
c) Miscellaneous
d) Estimate
View Answer
Explanation: The site amenities, diversion of roads, road side plantation and other facilities are covered under miscellaneous items, background and abstract are the important aspects, estimate are also very important.
Sanfoundry Global Education & Learning Series – Highway Engineering.
To practice all areas of Highway Engineering, here is complete set of 1000+ Multiple Choice Questions and Answers.
- Check Civil Engineering Books
- Apply for Civil Engineering Internship
- Check Highway Engineering Books
- Practice Civil Engineering MCQs