This set of Highway Engineering Multiple Choice Questions & Answers (MCQs) focuses on “Highway Planning in India”.
1. As per the Nagpur plan, the un-surfaced roads were meant for _____________
a) National highway
b) State highway
c) Major district road
d) Other district road and village road
View Answer
Explanation: The Nagpur plan classified the roads into two categories, category one was meant for the national highway, state highway and major district road. The un-surfaced roads were meant for other district roads and village roads.
2. The total length of the first category roads was calculated by adding up the sum of __________
a) NH+SH+MDR
b) NH+SH
c) SH*2
d) NH+2SH+MDR
View Answer
Explanation: The category one type of roads consisted of national highway, state highway and major district roads. The length was calculated by adding all the three types of roads.
3. What was the development allowance assumed in the Nagpur plan?
a) 10%
b) 20%
c) 15%
d) 25%
View Answer
Explanation: The development allowance was assumed as 15% and in this plan the length of the railway track also was deducted, this was not like the previous 20 year plan.
4. During the development of the roads maximum priority is given to which type of road?
a) National highway
b) State highway
c) Major district road
d) Village road
View Answer
Explanation: The maximum priority during construction of any road is given to national highway as they connect across length and breadth of the entire country.
5. The total length of highways in 2001 in km was __________
a) 56000
b) 56756
c) 56750
d) 57000
View Answer
Explanation: The total length of NH achieved in 2001 was 5700km against a planned length of 66000km.
6. The total area of a state is 2500km. Calculate the length of MDR.
a) 100 km
b) 200 km
c) 300 km
d) 400 km
View Answer
Explanation: Length of MDR=Area of the state/12.5=2500/12.5=200km.
7. The tertiary road system consists of __________
a) National highway
b) State highway
c) Major district road
d) Other district road and village road
View Answer
Explanation: As per the 2nd 20 year road development plan the primary system consists of national highway and state highway. The secondary system consists of state highway. The tertiary system consists of other district road and village road.
8. The ‘rural road development plan: Vision 2025’ aims to provide basic access to villages in how many phases?
a) One
b) Two
c) Three
d) Four
View Answer
Explanation: The Vision: 2025 aims at providing accessible facilities to villages in 3 phases by giving priority to the population in the village.
9. Expressways should be constructed along __________
a) Congested cities
b) Major traffic corridors
c) Along with highways
d) Small cities
View Answer
Explanation: Expressways should be constructed along major traffic corridors for the convenience of passengers to travel safely and comfortably.
10. The maximum number of cities and towns are connected by which type of highway?
a) National highway
b) State highway
c) Major district road
d) Village road
View Answer
Explanation: The national highway connects most of the cities and towns in the country. State highway connects in the state, village road in villages and other roads connect the remote areas.
Sanfoundry Global Education & Learning Series – Highway Engineering.
To practice all areas of Highway Engineering, here is complete set of 1000+ Multiple Choice Questions and Answers.
- Practice Civil Engineering MCQs
- Check Civil Engineering Books
- Check Highway Engineering Books
- Apply for Civil Engineering Internship