This set of Hazardous Waste Management Multiple Choice Questions & Answers (MCQs) focuses on “Risk Assessment – Hazard Identification”.
1. What is the main purpose of hazard identification?
a) To minimise the effect of a consequence
b) For better risk management
c) To characterize adverse effect of toxins
d) To reduce probability of occurrence
View Answer
Explanation: Hazard identification is the first step in risk assessment. The goal is to understand the concentration of toxins, spatial distribution and there movement.
2. The ____________ process determines whether exposure to a chemical can increase the incidence of adverse health effect.
a) Hazard identification
b) Exposure assessment
c) Toxicity assessment
d) Risk characterization
View Answer
Explanation: Hazard identification traces the path of the toxins and also determines the likelihood of occurrence in humans.
3. Which of the following data is not required for hazard identification?
a) Land use
b) Contaminant levels
c) Affected population
d) Estimation of risk
View Answer
Explanation: Estimation of risk is done at risk characterization whereas land use, contaminant level, affected population and biota data play a major role while identifying a hazard.
4. Hazard is defined as the probability of suffering harm or loss.
a) True
b) False
View Answer
Explanation: Risk is the probability of suffering harm whereas hazard is a potential source of harm.
5. Why does site history have to be considered for hazard identification?
a) To estimate the risk
b) To calculate carcinogenic exposure
c) To know the probable source and causes of contamination on site
d) For determination of remedial actions
View Answer
Explanation: Site history provides precise information about the activities that had been carried on the area. Most of the instance contamination is due to past activities on site.
6. What is the main objective of risk assessment?
a) To evaluate hazard and minimize the risks
b) Remediation of contaminated sites
c) Hazard management
d) To know source of pollutants
View Answer
Explanation: Risk assessment helps to understand possible problems and provides alternatives as well as control measures to reduce the accident.
7. What is the first stage of risk assessment?
a) Exposure assessment
b) Hazard identification
c) Toxicity study
d) Risk characterization
View Answer
Explanation: Hazard identification is the first stage of risk assessment. It provides clear understanding about chemical contaminants, their concentration and distribution in environment.
8. An incident can be called hazardous only when?
a) Stressor has the potential to cause harm to humans and ecological systems
b) Poses threat to surrounding
c) Monitoring is failed
d) Outburst of chemicals
View Answer
Explanation: An incident is called hazardous only when the contaminant poses threat to humans and ecological systems which may results in catastrophic.
9. The purpose of risk management is to identify potential problems before they occur so that risk-handling activities may be planned.
a) False
b) True
View Answer
Explanation: The main goal of risk management is to reduce the threats from an activity so that harm to the surrounding is minimized.
10. Hazard identification mainly focus on ______________
a) Chemical source and concentration
b) Chemical exposure
c) Chemical analysis
d) Chemical pathway
View Answer
Explanation: The main aim of hazard identification is to identify chemical source, concentration and its movement in environment.
Sanfoundry Global Education & Learning Series – Hazardous Waste Management.
To practice all areas of Hazardous Waste Management, here is complete set of 1000+ Multiple Choice Questions and Answers.
- Check Hazardous Waste Management Books
- Apply for Civil Engineering Internship
- Practice Civil Engineering MCQs
- Check Civil Engineering Books